The summary scope of work is to build up a team, base on the current problem achieve the solution, define the schedule and deadline, and budget the expense.
Build up a team, the team has the following members:
- A projector manager
- A network engineer to setup the network traffic control
- A asterisk engineer to improve the function of the VoIP
- A system administrator to install and configure the system environment
- A treasurer to control the budget
Base on the current problem and agreement between the users and project team to achieve the following solutions:
- Setup the network quality of service so the voice has higher priority to pass through the network tunnel.
- Setup secondly server for hosting the service of conference bridge so to share the load from the only server to increase the computing power resource.
- Setup the network traffic monitoring graphic so to continue watch the problem and to improve.
Define the schedule and deadline:
- 2 weeks: Project manager allocate the members.
- 2 weeks: System administrator specified the server specification and purchase the server.
- 2 weeks: System administrator install and configure the server.
- 4 weeks: Network engineer setup the network quality of service.
- 2 weeks: Network engineer verify the network quality of service.
- 4 weeks: Network engineer setup the network traffic monitoring graphic.
- 2 weeks: Network engineer verify the network traffic monitoring graphic.
- 4 weeks: Asterisk engineer setup the conference bridge server.
- 2 weeks: Asterisk engineer verify the conference bridge server.
Project will be done in 12 weeks. The meeting is scheduled every two weeks on Tuesday at 10:00AM to 12:00PM.
The budget:
Project Manager: $35 (per hour) x 70 (hours) = $2,450
System administrator: $ 35 (per hour) x 120 (hours) = $ 4,200.
Network engineer for four months: $30 (per hour) x 120 (hours) = $ 4,200.
Asterisk engineer for four months: $40 (per hour) x 100 (hours) = $ 4,000.
Treasurer: $25 (per hour) x 60 (hours) = $1,500.
1 server: $3950
Internet service for 3 months: 1,500 x 3 = $4,500
30 SIP Trunking + 20 DID = $15 x 30 + $20 = $470 x 3 months = $1,410
Total budget allocation: $26,210.
James, great project summary, very detailed and well laid out. -Jamie